[j-nsp] EX4200: VC "incremental upgrade" ?

Joe Hamelin joe at nethead.com
Mon Oct 25 13:55:32 EDT 2010


>From what I've seen you might be able to upgrade a VC member but once
it reboots with the new and different image it will no longer be part
of the VC.  So yeah, you can kinda do it but it's not much help over
just pulling the member and doing a stand alone upgrade.  The code has
to match on a VC.
--
Joe Hamelin, W7COM, Tulalip, WA, 360-474-7474



On Mon, Oct 25, 2010 at 6:31 AM, Philipp Geschke <juniper-nsp at pgmail.net> wrote:
> On Mon, 25 Oct 2010 17:10:46 +0400, Alexandre Snarskii <snar at snar.spb.ru>
> wrote:
>> Hi!
>>
>> Silly question: is it possible to perform "incremental upgrade"
>> on ex-series virtual-chassis ? I.e., upgrade some switches
>> (using 'request system software add member NN'), switchover
>> master to 'upgraded' part, then upgrade remaining switches ?
>
> Hi,
>
> no, that is currently not possible.
> You can always take single switches out of the stack and upgrade them
> outside of the stack, however, a hitless upgrade is not really possible.
>
>
> --
> Philipp
>
>
> _______________________________________________
> juniper-nsp mailing list juniper-nsp at puck.nether.net
> https://puck.nether.net/mailman/listinfo/juniper-nsp
>