[c-nsp] Delay in delivery of new routers

Eric Van Tol eric at atlantech.net
Tue Dec 15 12:07:46 EST 2020


Yes. We ordered some NCS routers back in September and the lead time was 6 weeks. Then it got pushed to December, now it's looking like late January. First it was COVID19 reasons, then we were told due to material shortages. Something similar with Juniper - 8 week lead time on MX204s.

-evt

On 12/15/20, 3:38 AM, "cisco-nsp on behalf of hank at interall.co.il" <cisco-nsp-bounces at puck.nether.net on behalf of hank at interall.co.il> wrote:

    EXTERNAL - Do not click links or open attachments from an unverified source/sender.

    We ordered 8 new ASR1009x at the end of July.

    Original delivery date was mid-September.  Then pushed to October,
    then pushed to November, then to Dec 15 and today we heard it has been
    pushed back to Jan 6, 2021.

    I am curious if others are encountering multi-month delays in delivery
    of Cisco routers.  If anyone has some knowledge as to what is going on
    and why the very long delays that would be helpful.

    Regards,
    Hank

    _______________________________________________
    cisco-nsp mailing list  cisco-nsp at puck.nether.net
    https://puck.nether.net/mailman/listinfo/cisco-nsp
    archive at http://puck.nether.net/pipermail/cisco-nsp/



More information about the cisco-nsp mailing list