It is my hope that I will be able to do something similar when testing out new versions of Call Manager, basically mimicing all route patterns etc on the new server and have a few phones testing things live and interacting with the production service.

However, I think it's quite an ordeal to migrate things piece meal. Test as much as you can, then upgrade the cluster. Be sure to have plenty of outs, i.e. backup and mirrored disks. We have new hardware and will be building the new publisher exactly as you mentioned. If you don't have new hardware, you should be able to take your publisher off-line during the upgrade and then plug it back in when you are done. Obviously database changes can't happen during that time and will affect things like call forwarding.

I think we have to begin letting our clients know that we have to upgrade and there will be changes seen. Many we will be able to document, but many may slip by our fingers because of lack of change documentation (sorry Cisco).

For your notes, you will have to do a two stage upgrade, from 3.3(3) -> 3.3(4) or 4.0(x) -> 4.1(2). We are choosing to go to 3.3(4) as our interim step.
  ----- Original Message ----- 
  From: chris donnelly 
  To: cisco-voip at puck.nether.net 
  Sent: Monday, January 24, 2005 4:57 AM
  Subject: [cisco-voip] Advice on CCM3 to CCM4 Migration please


  Hi, 

  Hopefully one of you guys have been through this and can recommend the most painless way forward.... 

  We have a customer who currently has an old 3.3.3 CCM Cluster with about 2000 phones hanging of it. 

  They need to go to CCM 4.x and want to prove the environment / product first by staging the new CCM 4 and then gradually moving users from the old cluster to the new cluster. The downside of this is that it is not a straightforward upgrade / replacement as the two clusters will live side by side for a while. 

  I have no problem with this apart from the sheer numbers involved. My initial thought was to use the BAT tool to import all data from the production cluster to the CCM4 cluster - but that still leaves me loads of stuff to cross-pollinate i.e. Route patterns, partitions etc...etc... 

  My second thought is to build the CCM4 cluster from the Upgrade 'Replace Server' option whilst building -but that forces me to use the old CCM3's machine name etc so the two clusters cannot live side by side....unless there is a way to build the CCM cluster by the 'Upgrade Replace Server' option and then rename the machine name and change IP addresses etc... 

  BTW I know everyone says that you cannot change machine names because of SQL (but has anyone actually tried this?) - there are snippets of info available on the web detailing how to change SQL machine names. 

  Any advice gratefully received. 

  Chris



------------------------------------------------------------------------------


  _______________________________________________
  cisco-voip mailing list
  cisco-voip at puck.nether.net
  https://puck.nether.net/mailman/listinfo/cisco-voip
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://puck.nether.net/pipermail/cisco-voip/attachments/20050124/f386a16d/attachment.html


More information about the cisco-voip mailing list