Gents,
good day.
A customer of mine has in production MX480, SRX3600 (cluster via WAN L2
among the two DC), EX8200 in all of the two DC and is asking me a
confirmation that it is currently possible to simulate a Disaster Recovery
issue just powering-off the devices without correct halting.
I’m trying to force them to run a correct halting but it seems they have a
very strict time (few minutes) to deactivate the Datacenter during the DR
procedure and are pressing me to validate.
I’m looking for:
1) Official juniper documentation about the issue that occurs if a not
graceful halting is given
2) Experience in this kind of issues on the family MX, SRX in cluster
and EX8k
3) Any recommendation/help to force my customer…
Greetings
James